Which of the following is not a part of process change?

A. Introducing new practices, methods or processes

B. Introducing new team members to existing project

C. Introducing or removing deliverable

D. Introducing new roles or responsibilities

Answer: Option B


This Question Belongs to Computer Science >> Software Engineering