Which of the following lasts for the duration of the project and covers the development process?
A. Monitoring all key parameters like cost, schedule, risks
B. Taking corrective actions when needed
C. Providing information on the development process in terms of metrics
D. All of the mentioned
Answer: Option A
Which of the following is not a phase of the Software Development Life Cycle (SDLC)?
A. Planning
B. Analysis
C. Testing
D. Maintenance
What does UML stand for in software engineering?
A. Unified Modeling Language
B. Universal Modeling Language
C. Unique Modeling Language
D. Unified Management Language
Which software development model is also known as the linear-sequential life cycle model?
A. Agile
B. Waterfall
C. Spiral
D. RAD (Rapid Application Development)
In which phase of the SDLC is the feasibility study conducted?
A. Planning
B. Design
C. Implementation
D. Maintenance