Which of the following represent correct sequence of SHRM process?
1. Identifying the tools required.
2. Evaluate the capability of HR.
3. Develop an understanding of the goals of the organisation.
4. Analysing current capacity.
5. Estimating future human resource requirements of the company.
6. Implementing strategies.
A. 2, 3, 4, 1, 6, 5
B. 3, 2, 4, 5, 1, 6
C. 3, 4, 2, 6, 1, 5
D. 3, 4, 2, 5, 1, 6
Answer: Option B