"Which of the following would explain an adverse variable production overhead efficiency variance?
1 Employees were of a lower skill level than specified in the standard
2 Unexpected idle time resulted from a series of machine breakdown
3 Poor Quality material was difficult to process"
A. (1), (2) and (3)
B. (1) and (2)
C. (2) and (3)
D. (1) and (3)
Answer: Option D