Which one of the following statements is not correct with regard to heading and henching method of tunnelling?
A. Driving of tunnel is done in two portions of its section
B. Driving the top portion is done in advance of the bottom portion
C. The holes in head and bench are loaded together with explosive for blasting
D. Firing of head holes is done just before the bench holes are fired
Answer: Option D