Works overhead is Rs 40,000, total machine hours is 8500 hours and time allowed for machine setting is 500 houRs What is the machine rate?

A. Rs. 2 per hour

B. Rs. 3 per hour

C. Rs. 4 per hour

D. Rs. 5 per hour

Answer: Option D

Solution(By Examveda Team)

Machine hour rate = Works overhead / Machine hour
= 40000 / (8500 - 500) = Rs. 5 per hour.

This Question Belongs to Commerce >> Costing

Join The Discussion

Comments ( 1 )

  1. Naaresh Kumar
    Naaresh Kumar :
    6 years ago

    machine hour rate= overhead cost/Actual machine hours

    =40000/8500-500= Rs.5p hr