45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?
A. 6 days
B. 8 days
C. $${\text{6}}\frac{2}{3}{\text{ days}}$$
D. $${\text{7}}\frac{3}{4}{\text{ days}}$$
Answer: Option C
Solution(By Examveda Team)
According to the question,Let the remaining work is complete in D days
$${\text{4}}{{\text{5}}_{{\text{men}}}} \times {\text{1}}{{\text{6}}_{{\text{days}}}}$$ = $$\left( {{\text{4}}{{\text{5}}_{{\text{men}}}} \times {{\text{4}}_{{\text{days}}}}} \right)$$ + $${\left( {{\text{45}} + {\text{36}}} \right)_{{\text{men}}}}$$ $$ \times {\text{D}}$$
$$\eqalign{ & \Rightarrow \frac{{540}}{{81}} = {\text{D}} \cr & \Rightarrow {\text{D}} = 6\frac{2}{3}{\text{ days}} \cr} $$