A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
A. 30 days
B. 40 days
C. 60 days
D. 70 days
Answer: Option C
Solution(By Examveda Team)
$$\eqalign{ & {\text{Let}}\,{\text{A's}}\,{\text{1}}\,{\text{day's}}\,{\text{work}} = x\,{\text{and}} \cr & {\text{B's}}\,{\text{1}}\,{\text{day's}}\,{\text{work}} = y \cr & {\text{Then}},\,x + y = \frac{1}{{30}} \cr & 16x + 44y = 1 \cr & {\text{Solving}}\,{\text{these}}\,{\text{two}}\,{\text{equations,}}\,{\text{we}}\,{\text{get}} \cr & x = \frac{1}{{60}}\,{\text{and}}\,y = \frac{1}{{60}} \cr & \therefore {\text{B's}}\,{\text{1}}\,{\text{day's}}\,{\text{work}} = \frac{1}{{60}} \cr & {\text{Hence,}}\,{\text{B}}\,{\text{alone}}\,{\text{shall}}\,{\text{finish}}\,{\text{the}} \cr & {\text{whole}}\,{\text{work}}\,{\text{in}}\,{\text{60}}\,{\text{days}} \cr} $$Join The Discussion
Comments ( 1 )
Related Questions on Time and Work
A. 18 days
B. 24 days
C. 30 days
D. 40 days
is there any other way to attempt this question
if i dont want to solve the question by equation form