A can do $$\frac{1}{4}$$ part of a work in 9 days. B can do $$\frac{2}{3}$$ part of the same work in 28 days. Working together, in how many days can A and B complete the whole work?

A. $$\frac{{252}}{{13}}{\text{ days}}$$

B. $$\frac{{261}}{{15}}{\text{ days}}$$

C. $$\frac{{262}}{{11}}{\text{ days}}$$

D. $$\frac{{198}}{{17}}{\text{ days}}$$

Answer: Option A

Solution (By Examveda Team)

Time and Work mcq question image
(A + B) = $$\frac{{252}}{{13}}$$