A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?
A. $${\text{6}}\frac{3}{5}$$
B. $${\text{8}}\frac{1}{2}$$
C. $${\text{10}}\frac{1}{5}$$
D. $${\text{13}}\frac{1}{2}$$
Answer: Option C
Solution(By Examveda Team)
$$\eqalign{ & {\text{B's 3 day's work}} \cr & = \left( {\frac{1}{{21}} \times 3} \right) \cr & = \frac{1}{7} \cr & {\text{Remaining work}} \cr & = \left( {1 - \frac{1}{7}} \right) \cr & = \frac{6}{7} \cr & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{14}} + \frac{1}{{21}}} \right) \cr & = \frac{5}{{42}} \cr} $$Now, $$\frac{5}{{42}}$$ work is done by A and B in 1 day
$$\eqalign{ & \therefore \frac{6}{7}{\text{ work is done by A and B in}} \cr & = \left( {\frac{{42}}{5} \times \frac{6}{7}} \right) \cr & {\text{ = }}\frac{{36}}{5}{\text{ days}} \cr & {\text{Hence, total time taken}} \cr & = \left( {3 + \frac{{36}}{5}} \right){\text{days}} \cr & = 10\frac{1}{5}{\text{days}}{\text{.}} \cr} $$
Join The Discussion
Comments ( 1 )
Related Questions on Time and Work
A. 18 days
B. 24 days
C. 30 days
D. 40 days
At first (A+B) work together
then B alone do last 3 days work
so, if you calculate at first last 3 day's work that will be wrong process.
NB. B would do only remain work not (1/21*3)=1/7 part (it is B's rate of work that he/she can do any 3 days)