Examveda
Examveda

A can do a work in 36 days, B in 18 days and C in 12 days. Every 2nd day B and every 3rd day C, helps A .Then in how many days the work will be completed?

A. 12

B. 14

C. 10

D. 8

Answer: Option B

Solution(By Examveda Team)

Let to work Total Work = 36
One day work of A = $$\frac{{36}}{{36}}$$ = 1 unit/day
One day work of B = $$\frac{{36}}{{18}}$$ = 2 unit/day
One day work of C = $$\frac{{36}}{{12}}$$ = 3 unit/day
In 3 days cycle total work done is A, A + B, A + C = 1 + (1 + 2) + (1 + 3) = 8 unit/Cycle
∴ 32 units of the work completed in 4 cycle and reminder 4 units of works in next two days.
1 cycle = 3 days
∴ 4 cycle = 12 days
And remaining 4 unit work done in next two days. In days 13, A will work 1 unit and in day 14, A and B will work 3 units.
Total number the day required to complete the work in the given condition is 14 days

This Question Belongs to Arithmetic Ability >> Time And Work

Join The Discussion

Comments ( 6 )

  1. Learning Point
    Learning Point :
    3 years ago

    Ans is 12 days

  2. Dinesh Chandra
    Dinesh Chandra :
    4 years ago

    Total work 36 units
    In 12 days work done=12*1+6*2+4*3
    =>36 units
    So,required days 12 (ans)

  3. Lalitha Mocherla
    Lalitha Mocherla :
    4 years ago

    @subbrato kumer. B works 3 days and c works 2 days how it is obtained??

  4. Ismail Hossain
    Ismail Hossain :
    4 years ago

    Answer-12days

  5. Sajitha Menon
    Sajitha Menon :
    4 years ago

    During the 6th, 12th.....days all three of them would have worked together. So the number of days would be less....???

  6. Subbrato Kumer
    Subbrato Kumer :
    4 years ago

    LCM of 2 and 3=6
    in first 6 days A work all the day, B works 3 days and C works for 2 days
    A+B+C in first 6 days Done=(6/36+3/18+2/12)=1/2 part

    1/2 part can Complete in 6 days
    so, 1 part Complete in 6X2=12 Days

Related Questions on Time and Work