A can do a work in 36 days, B in 18 days and C in 12 days. Every 2nd day B and every 3rd day C, helps A .Then in how many days the work will be completed?
A. 12
B. 14
C. 10
D. 8
Answer: Option B
Solution(By Examveda Team)
Let to work Total Work = 36One day work of A = $$\frac{{36}}{{36}}$$ = 1 unit/day
One day work of B = $$\frac{{36}}{{18}}$$ = 2 unit/day
One day work of C = $$\frac{{36}}{{12}}$$ = 3 unit/day
In 3 days cycle total work done is A, A + B, A + C = 1 + (1 + 2) + (1 + 3) = 8 unit/Cycle
∴ 32 units of the work completed in 4 cycle and reminder 4 units of works in next two days.
1 cycle = 3 days
∴ 4 cycle = 12 days
And remaining 4 unit work done in next two days. In days 13, A will work 1 unit and in day 14, A and B will work 3 units.
Total number the day required to complete the work in the given condition is 14 days
Join The Discussion
Comments ( 6 )
Related Questions on Time and Work
A. 18 days
B. 24 days
C. 30 days
D. 40 days
Ans is 12 days
Total work 36 units
In 12 days work done=12*1+6*2+4*3
=>36 units
So,required days 12 (ans)
@subbrato kumer. B works 3 days and c works 2 days how it is obtained??
Answer-12days
During the 6th, 12th.....days all three of them would have worked together. So the number of days would be less....???
LCM of 2 and 3=6
in first 6 days A work all the day, B works 3 days and C works for 2 days
A+B+C in first 6 days Done=(6/36+3/18+2/12)=1/2 part
1/2 part can Complete in 6 days
so, 1 part Complete in 6X2=12 Days