A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
A. 5
B. $$5\frac{1}{2}$$
C. 6
D. 8
E. None of these
Answer: Option C