A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is

A. 500 m3

B. 1000 m3

C. 1500 m3

D. 2000 m3

Answer: Option D


This Question Belongs to Civil Engineering >> Estimating And Costing

Join The Discussion

Comments ( 7 )

  1. Vince Dopo
    Vince Dopo :
    3 years ago

    I don't get it the right answer . It is a 1500m3 or 2000m3 ? Can anyone tell me the solution

  2. Shouib Hassan
    Shouib Hassan :
    3 years ago

    Option c is correct
    Original vol. Comes out 2000m3
    But we know
    Cutting vol. =(1/4)*original volume
    So putting the values we get
    Cutting vol. =(1/4)* 2000=500
    So box cutting in road crust=2000-500=1500

  3. Yuva Shree
    Yuva Shree :
    3 years ago

    Original volvume = 1000 cu m
    Cutoff volume = 500 cu m
    So 2000-500 1500

  4. Shubham Patil
    Shubham Patil :
    4 years ago

    Orginal volume = 1000m * 8m * (15cm+10cm),
    = 1000 * 8 * 0.25cum,
    = 2000 cum

    Cutt-off volume = (1/4) * original volume.
    = (1/4) * 2000cum,
    = 500cum

    So, Box cutting in road curst = (2000-500)
    = 1500cum

  5. Amit Saini
    Amit Saini :
    5 years ago

    yes it should be 2000
    because if we calculate total thickness that will be .25m
    and we have given width is 8m
    length is 1000m
    so total volume is 1000*8*.25 = 2000

  6. Engr. Shakhawat
    Engr. Shakhawat :
    5 years ago

    how it .
    Ans should be D): 2000 Cu M

  7. Aspi Rout
    Aspi Rout :
    5 years ago

    How it .
    Ans should be D -2000 M3