A completes $$\frac{7}{{10}}$$ of the work 15 days. Then he completes the remaining work the help of B in 4 days. The time required for A and B together to complete the entire work is = ?
A. $${\text{8}}\frac{1}{4}{\text{days}}$$
B. $$10\frac{1}{2}{\text{days}}$$
C. $$12\frac{2}{3}{\text{days}}$$
D. $$13\frac{1}{3}{\text{days}}$$
Answer: Option D
Solution(By Examveda Team)
$$\eqalign{ & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 4 day's work}} \cr & = \left( {1 - \frac{7}{{10}}} \right) \cr & = \frac{3}{{10}} \cr & \left( {{\text{A}} + {\text{B}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{3}{{10}} \times \frac{1}{4}} \right) \cr & = \frac{3}{{40}} \cr & {\text{Remaining work }} \cr & = \left( {1 - \frac{3}{{10}}} \right) \cr & = \frac{7}{{10}}{\text{ }} \cr & \left( {{\text{B}} + {\text{C}}} \right){\text{'s 1 day's work}} \cr & = \left( {\frac{1}{{15}} + \frac{1}{{20}}} \right) \cr & = \frac{7}{{60}} \cr} $$Hence, A an B together take $$ = \frac{{40}}{3} = 13\frac{1}{2}$$ days to complete the entire work.
Related Questions on Time and Work
A. 18 days
B. 24 days
C. 30 days
D. 40 days
Join The Discussion