Examveda
Examveda

A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?

A. 23 days

B. 37 days

C. $$37\frac{1}{2}$$ days

D. 40 days

Answer: Option C

Solution(By Examveda Team)

$$\eqalign{ & {\text{Whole}}\,{\text{work}}\,{\text{is}}\,{\text{done}}\,{\text{by}}\,{\text{A}}\,{\text{in}} \cr & = {20 \times \frac{5}{4}} = 25\,{\text{days}} \cr & {\text{Now}},\,\left( {1 - \frac{4}{5}} \right)\,\,i.e., \cr & \frac{1}{5}\,{\text{work}}\,{\text{is}}\,{\text{done}}\,{\text{by}}\,{\text{A}}\,{\text{and}}\,{\text{B}}\,{\text{in}}\,{\text{3}}\,{\text{days}} \cr & {\text{Whole}}\,{\text{work}}\,{\text{will}}\,{\text{be}}\,{\text{done}}\,{\text{by}}\,{\text{A}}\,{\text{and}}\,{\text{B}}\,{\text{in}} \cr & = \left( {3 \times 5} \right) = 15\,{\text{days}} \cr & {\text{A's}}\,{\text{1}}\,{\text{day's}}\,{\text{work}} = \frac{1}{{25}}, \cr & \left( {{\text{A + B}}} \right)\,{\text{'s}}\,{\text{1}}\,{\text{day's}}\,{\text{work}} = \frac{1}{{15}} \cr & \therefore {\text{B's}}\,{\text{1}}\,{\text{day's}}\,{\text{work}} \cr & = {\frac{1}{{15}} - \frac{1}{{25}}} = \frac{4}{{150}} = \frac{2}{{75}} \cr & {\text{So,}}\,{\text{B}}\,\,{\text{alone}}\,{\text{would}}\,{\text{do}}\,{\text{the}}\,{\text{work}}\,{\text{in}} \cr & \frac{{75}}{2} = 37\frac{1}{2}\,{\text{days}} \cr} $$

This Question Belongs to Arithmetic Ability >> Time And Work

Join The Discussion

Comments ( 2 )

  1. Bidya Sagar
    Bidya Sagar :
    3 years ago

    For 20% work,
    A and A+B take 5 days and 3 days resp.
    Then, B takes (5×3)/(5-3)days i.e. 7.5 days
    So, for 100% work takes ( 7.5×5) days
    Final Answer: 37.5 days.
    Thanks !!

  2. Debendra Kumar
    Debendra Kumar :
    4 years ago

    80% work done by A= 20 days
    100% work will be done 20/80X100=25days
    Remaining work 20% do A and B In 3days
    100% work work will be completed A&B in 3/20X100=15days
    LCM method
    A------>25
    A&B------->15
    LCM 75 so A's efficiency 3 and A&B is 5
    B's efficiency 5-3=2
    B can do whole work is 75/2=37.5



Related Questions on Time and Work