ExamVeda
Login
Home
This question belongs to Arithmetic Ability Time And Work
Time and Work
?

A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:

Answer & Solution
Correct Answer: Option C
Let x be the required number of days
Given,
12 men and 12 women can complete a work separately in 14 days and 21 days respectively
Then,
12 men's 1 day work = $$\frac{1}{{14}}$$
And,
12 women's 1 day work = $$\frac{1}{{21}}$$
Then ,
12 women's 3 days work = $$\frac{3}{{21}}$$ = $$\frac{1}{7}$$

The remaining work = $$1 - \frac{1}{7}$$  = $$\frac{6}{7}$$
Man's group leaves 3 days before the completion of work
That is, they were working together for x - 3 days
Thus, we have $$\frac{1}{7}$$ work left to be done in last 3 days by the women's group. This also means $$\frac{6}{7}$$ th of work has been done by both the groups (before men left)
Now, (12 men + 12 women)'s 1 day work = $$\frac{1}{{14}} + \frac{1}{{21}}$$   = $$\frac{5}{{42}}$$
i.e., $$\frac{5}{{42}}$$ work is done by 2 groups in 1 day.
So, $$\frac{6}{7}$$ of work is done by 2 groups together in $$\frac{{42}}{5} \times \frac{6}{7}$$   = $$\frac{{36}}{5}$$ days
Total time take to complete the work will be
= $$\frac{{36}}{5}$$ + 3 = $$\frac{{51}}{5}$$
Examveda
Question posted by Examveda
Community

Join the Discussion

3 Comments
স্পর্শিয়া শারমিন
স্পর্শিয়া শারমিন 6 years ago
Suppose total time take to complete the work = x
(12*x-3)/12*14 + (12*x)/ 12*21 = 1
(x-3)/14 + x/ 21 =1
(3x -9+2x )/42 =1
5x = 51
X = 51/ 5
Md. Saiful
Md. Saiful 8 years ago
12 men work 1 day = 1/14
12 women work 1 day = 1/21
Let, the work complete in X days
Men are left 3 days before, that means ( x-3)
According to the question,
X-3/14 +x/21=1
Then, x= 51/5
The work complete 51/5 days
Savio N
Savio N 10 years ago
Ur ans is incomplete I think