A group of men decided to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?
Answer & Solution
Correct Answer:
Option
B
Let X be the initial number of men then,
According to the question,
4X = X + (X - 20) + (X - 40) + (X - 60) + (X - 80) + (X - 100) + (X - 120)
⇒ 4X = 7X - 420
⇒ 3X = 420
⇒ X = $$\frac{{420}}{3}$$
⇒ X = 140 men
Join the Discussion
Login to post a comment or share your explanation.
LoginTotal work =4X (since they stipulate they (x people) can complete the work in 4 days )
We know that
N=7 , First term(a)=X , Common difference (d)= -20
Thus
4x = (7/2)*(2x+(7-1)×(-20)) [ using arithmetic progression ]
Solving for X , we will get X=140 person