A profitability index (PI) of .95 for a project means
A. The project's costs (cash outlay) are less than the present value of the project's benefits
B. The project's NPV is greater than zero
C. The project's NPV is greater than one
D. The project returns are 95 paise in present value for each current rupee invested
Answer: Option D