Examveda
Examveda

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

A. 43

B. 45

C. 55

D. 68

E. 60

Answer: Option D

Solution(By Examveda Team)

Variation Method:
In 100 days only 2.5 km road i.e. 16.66 % of work has been completed
Men Days Road (km)
45 100↓ 2.5
x↑ 200 12.5↑

Arrows show the directions of variation of quantity with respect to each other
$$\frac{{\text{x}}}{{45}} = \frac{{100 \times 12.5}}{{200 \times 2.5}}$$
x = 113 men;
Required men to be increased,
= 113 - 45
= 68

This Question Belongs to Arithmetic Ability >> Time And Work

Join The Discussion

Comments ( 3 )

  1. Satwikprasad Mohanty
    Satwikprasad Mohanty :
    3 years ago

    @Roger Oliver bro you already found that days for 200 days so don't need to subtract any further .

  2. Roger Oliver
    Roger Oliver :
    5 years ago

    I see my error, 22500 / 200 = 112.5, rounding up to 113 - 45 already contracted = 68. :-)

  3. Roger Oliver
    Roger Oliver :
    5 years ago

    45 men x 100 days = 4500 man days
    4500 man days / 2.5 km = 1800 man days per km
    12.5 km to build * 1800 man days per km = 22,500 man days to complete the road
    22,500 man days / 200 days = 67.5 men, rounding to 68 men working 200 days to complete the road
    Why wouldn't the number of extra men be 68 - 45 = 23?

Related Questions on Time and Work