ExamVeda
Login
Home
This question belongs to Arithmetic Ability Time And Work
Time and Work
?

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

Answer & Solution
Correct Answer: Option D
Variation Method:
In 100 days only 2.5 km road i.e. 16.66 % of work has been completed
Men Days Road (km)
45 100↓ 2.5
x↑ 200 12.5↑

Arrows show the directions of variation of quantity with respect to each other
$$\frac{{\text{x}}}{{45}} = \frac{{100 \times 12.5}}{{200 \times 2.5}}$$
x = 113 men;
Required men to be increased,
= 113 - 45
= 68
Examveda
Question posted by Examveda
Community

Join the Discussion

3 Comments
Satwikprasad Mohanty
Satwikprasad Mohanty 5 years ago
@Roger Oliver bro you already found that days for 200 days so don't need to subtract any further .
Roger Oliver
Roger Oliver 7 years ago
I see my error, 22500 / 200 = 112.5, rounding up to 113 - 45 already contracted = 68. :-)
Roger Oliver
Roger Oliver 7 years ago
45 men x 100 days = 4500 man days
4500 man days / 2.5 km = 1800 man days per km
12.5 km to build * 1800 man days per km = 22,500 man days to complete the road
22,500 man days / 200 days = 67.5 men, rounding to 68 men working 200 days to complete the road
Why wouldn't the number of extra men be 68 - 45 = 23?