Examveda

As per IS : 1343, total shrinkage for a pre-tensioned beam, is

A. 3.0 × 10-2

B. 3.0 × 10-3

C. 3.0 × 10-5

D. 3.5 × 10-5

Answer: Option D


This Question Belongs to Civil Engineering >> RCC Structures Design

Join The Discussion

Comments (4)

  1. Sharik Shakeel
    Sharik Shakeel:
    2 years ago

    0.0003

  2. Abhishek Raj
    Abhishek Raj:
    5 years ago

    Wrong ans

  3. Muhammad Saqib
    Muhammad Saqib:
    6 years ago

    It's 0.0003 shrinkage

  4. Girish Pakki
    Girish Pakki:
    7 years ago

    No answer b : 0.0003

Related Questions on RCC Structures Design

If the shear stress in a R.C.C. beam is

A. Equal or less than 5 kg/cm2, no shear reinforcement is provided

B. Greater than 4 kg/cm2, but less than 20 kg/cm2, shear reinforcement is provided

C. Greater than 20 kg/cm2, the size of the section is changed

D. All the above