Examveda
Examveda

Consider the following operations:
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete
The correct sequence of these operations in tunnel construction is

A. 1, 2, 4, 3, 5

B. 1, 3, 2, 4, 5

C. 1, 2, 3, 4, 5

D. 1, 3, 4, 2, 5

Answer: Option C


Join The Discussion

Related Questions on Construction Planning and Management

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{2}$$

B. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{3}$$

C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{4}$$

D. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{5}$$

E. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$