ExamVeda
Login
Home
1
The normal time required for the completion of project in the above problem is
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
2
If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be
Discuss
Answer & Solution
Answer: Option E
No explanation is given for this question. Let's Discuss on Board
3
A construction schedule is prepared after collecting
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board
4
If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
5
Bar charts are suitable for
Discuss
Answer & Solution
Answer: Option A
Solution:
Bar charts (also called Gantt charts) are simple graphical schedules used to show the start time, finish time, and duration of different construction activities.

They are best suited for minor or small construction works because the number of activities is limited, making the schedule easy to prepare and understand.

For large or complex projects, bar charts become difficult to manage since they do not clearly show the relationship or dependency between activities. In such cases, network planning techniques like PERT (Program Evaluation and Review Technique) or CPM (Critical Path Method) are preferred.

Easy Trick to Remember:
Small Project → Bar Chart
Large Project → PERT / CPM

Hence, bar charts are most suitable for minor works, making Option A the correct answer.
6
The first stage of a construction, is
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
7
A father notes that when his teenage daughter uses the telephone, she takes not less than 6 minutes for a call and som? times as much as an hour. Fifteen minutes call are more frequent than calls of any other duration. If these phone calls were an activity in PERT project, then phone calls expected duration will be
Discuss
Answer & Solution
Answer: Option C
No explanation is given for this question. Let's Discuss on Board
8
The probability of completion of any activity within its expected time is
Discuss
Answer & Solution
Answer: Option A
No explanation is given for this question. Let's Discuss on Board
9
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
Discuss
Answer & Solution
Answer: Option B
No explanation is given for this question. Let's Discuss on Board
10
For the network shown in the given figure, the expected time for the activity
Construction Planning and Management mcq question image
Discuss
Answer & Solution
Answer: Option D
No explanation is given for this question. Let's Discuss on Board