Dispatching authorises the start of production operations by
1. release of material and components from stores to first process.
2. release of material from process to process.
3. issue of drawings instruction sheets.
Which of the following is/are true?
A. Only 1
B. Only 2
C. Bioth 1 and 2
D. All of the above
Answer: Option D