Directions (1 - 5): Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.
Table Chart direction image

Examveda
Examveda

Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. the number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)

A. 150%

B. 225%

C. 270%

D. 240%

Answer: Option A

Solution(By Examveda Team)

% change in the cost incurred in the fifth month,
$$\eqalign{ & = \frac{100000-40000}{40000}\times100 \cr & = 150\% \cr} $$

This Question Belongs to Data Interpretation >> Table Chart

Join The Discussion

Comments ( 3 )

  1. Koustav Sarkar
    Koustav Sarkar :
    2 years ago

    5th Month Cost per person =10000 there were 4 persons
    Thus cost =40000
    Now 5th Month 5 persons at 20000 thus 100000
    thus the %change =(100000-40000)/40000*100;