Directions (1 - 5): Sarp Infotech Solutions Software Company before selling a package to its clients, follows the given schedule.
Due to overrun in design, the stage took 3 months, i.e., months 3, 4 and 5. the number of people working on design in the fifth month was 5. Calculate the percentage change in cost incurred in the fifth month. (Due to improvement in Coding technique, this stage was completed in month 6-8 only.)
A. 150%
B. 225%
C. 270%
D. 240%
Answer: Option A
Solution(By Examveda Team)
% change in the cost incurred in the fifth month, $$\eqalign{ & = \frac{100000-40000}{40000}\times100 \cr & = 150\% \cr} $$Join The Discussion
Comments ( 3 )
Related Questions on Table Chart
5th Month Cost per person =10000 there were 4 persons
Thus cost =40000
Now 5th Month 5 persons at 20000 thus 100000
thus the %change =(100000-40000)/40000*100;