Dummy activities are used in a network to
A. facilitate computation of slacks
B. satisfy precedence requirements
C. determine project completion time
D. avoid use of resources
Answer: Option B
A. facilitate computation of slacks
B. satisfy precedence requirements
C. determine project completion time
D. avoid use of resources
Answer: Option B