Five jobs are to be scheduled in two machines in a production unit. All the five jobs undergo processing in both the machines (shop floor). The table given below provides information on the processing time in both the machines.
Job No. | Processing Time | |
Machine 1 | Machine 2 | |
1 | 4 | 7 |
2 | 6 | 3 |
3 | 2 | 3 |
4 | 7 | 7 |
5 | 8 | 6 |
A. Job 3 Job 1 Job 4 Job 5 Job 2
B. Job 3 Job 5 Job 4 Job 1 Job 2
C. Job 5 Job 3 Job 1 Job 2 Job 4
D. Job 5 Job 1 Job 2 Job 3 Job 4
Answer: Option A