Five jobs are to be scheduled in two machines in a production unit. All the five jobs undergo processing in both the machines (shop floor). The table given below provides information on the processing time in both the machines.
Job No. Processing Time
Machine 1 Machine 2
1 4 7
2 6 3
3 2 3
4 7 7
5 8 6
Identify the best sequence using Johnson's rule.

A. Job 3 Job 1 Job 4 Job 5 Job 2

B. Job 3 Job 5 Job 4 Job 1 Job 2

C. Job 5 Job 3 Job 1 Job 2 Job 4

D. Job 5 Job 1 Job 2 Job 3 Job 4

Answer: Option A


This Question Belongs to Management >> Operations Research