For 100 sq. m cement concrete (1 : 2 : 4) 4 cm thick floor, the quantity of cement required, is

A. 0.90 m3

B. 0.94 m3

C. 0.98 m3

D. 1.00 m3

Answer: Option B


This Question Belongs to Civil Engineering >> Estimating And Costing

Join The Discussion

Comments ( 3 )

  1. KANHA L
    KANHA L :
    3 years ago

    Volume of cement concrete is =0.04*100=4cum
    10%extra for unevenness and loss =4.4cum
    Loose volume =50%extra =4.4*1.5=6.6cum
    Volume of cement =6.6/(1+2+4)=0.942cum

  2. Kd Kdurai
    Kd Kdurai :
    3 years ago

    Totel volume = 7, thickness of floor = 4
    Stp1. 1÷7 = 0.1428
    Stp2. 2÷7 = 0.2857
    Stp3. 4÷7 = 0.5714
    All values are multiple and × 4
    =0.1428×0.2857×0.5714×4
    =0.09324
    Assume = 0.094
    Ans = 0.94m^3

  3. Tulsi Garg
    Tulsi Garg :
    3 years ago

    Generally to calculate the Cement, fine aggregate and coarse aggregate the following method will be followed,

    Wet Qty. of concrete = 100 Sqm * 0.04m thickness = 4.00 Cum
    To get the dry volume of concrete, generally wet volume of concrete will be multiplied by 150%.

    Therefore 4.00 Cum * 150% = 6.00 Cum.

    Cement Qty. = Dry volume of concrete / ( Sum of the ratio values).

    = 6.00 /( 1+2+4).
    = 0.857 Cum of Cement i.e.25 No. of bags.

    But here they considered 164.5% instead of 150%.

    Dry volume of concrete = 4 * 164.5% = 6.58 Cum.

    Cement Qty. = 6.58/ (1+2+4) = 0.94 Cum