For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is

A. 0.200 m3

B. 0.247 m3

C. 0.274 m3

D. 0.295 m3

Answer: Option C


This Question Belongs to Civil Engineering >> Estimating And Costing

Join The Discussion

Comments ( 2 )

  1. Sona Date
    Sona Date :
    4 years ago

    Net volume of mortar=100*12/1000=1.2cub.m
    Add 30%mortar for joint filling =30/100*1.2+1.2=1.56 this is the total wet vloume
    Now add 30%to wet vloume to obtain dry volume of mortar hence
    Dry vloume =30/100*1.56+1.56=2.028
    And now volume of cement =2.028/1+6*1=0.274

  2. Akhilesh Verma
    Akhilesh Verma :
    4 years ago

    Solve