For an open pit operation the value of metal is Rs. 210/kg, and recoverable grade is 1.2%. Production cost per tonne of ore inclusive of mining and processing but excluding stripping is Rs. 2000. If the break even stripping ratio is 3.49 m3/te. then the stripping cost is (lte = 1000 kg)

A. Rs. 149/m3

B. Rs. 140/m3

C. Rs. 72/m3

D. Rs. 60/m3

Answer: Option A