For an open pit operation the value of metal is Rs. 210/kg, and recoverable grade is 1.2%. Production cost per tonne of ore inclusive of mining and processing but excluding stripping is Rs. 2000. If the break even stripping ratio is 3.49 m3/te. then the stripping cost is (lte = 1000 kg)
A. Rs. 149/m3
B. Rs. 140/m3
C. Rs. 72/m3
D. Rs. 60/m3
Answer: Option A
Related Questions on Mine Economics
A. Salting
B. Speculative rate of return
C. Depreciation
D. Ore reserve calculation
Join The Discussion