For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

A. 1

B. 2

C. 3

D. 4

Answer: Option D

Solution(By Examveda Team)

This is the correct answer. In construction project management using a bar chart (Gantt chart), each activity is represented by a horizontal bar. The activities mentioned in the question include:

1. Supply of materials for concrete
2. Formwork, reinforcing, and placing of concrete
3. Removal of formwork
4. Curing of concrete
Each of these activities requires a separate bar on the chart.

Join The Discussion

Comments ( 5 )

  1. Amol Pawar
    Amol Pawar :
    3 months ago

    Answer is A because all activities are depends on previous activity
    ie All activity will cover in single bar only

  2. Kaushik Gohain
    Kaushik Gohain :
    3 years ago

    It should be 4. Form work , reinforcement placing and binding , concreting,curing

  3. Pankaj Nath
    Pankaj Nath :
    3 years ago

    they have asked no of bars in bar chart..how they got the ans option a

  4. Gaurav Datar
    Gaurav Datar :
    4 years ago

    All of the above item should be attempt in 1 bar chart

  5. Rohit Bagal
    Rohit Bagal :
    4 years ago

    Plz explain how...?

Related Questions on Construction Planning and Management

If to, tp and tm are the optimistic, pessimistic and most likely time estimates of an activity respectively, the expected time t of the activity will be

A. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{2}$$

B. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{3}$$

C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{4}$$

D. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{5}$$

E. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$