For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is
A. 1
B. 2
C. 3
D. 4
Answer: Option D
Solution (By Examveda Team)
This is the correct answer. In construction project management using a bar chart (Gantt chart), each activity is represented by a horizontal bar. The activities mentioned in the question include:1. Supply of materials for concrete
2. Formwork, reinforcing, and placing of concrete
3. Removal of formwork
4. Curing of concrete
Each of these activities requires a separate bar on the chart.

Answer is A because all activities are depends on previous activity
ie All activity will cover in single bar only
It should be 4. Form work , reinforcement placing and binding , concreting,curing
they have asked no of bars in bar chart..how they got the ans option a
All of the above item should be attempt in 1 bar chart
Plz explain how...?