If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?
A. 18 days
B. 15 days
C. 16 days
D. 20 days
Answer: Option C
Solution (By Examveda Team)
27 × 8 × 12 = 18 × 9 × xx = 16 days