If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?

A. 18 days

B. 15 days

C. 16 days

D. 20 days

Answer: Option C

Solution (By Examveda Team)

27 × 8 × 12 = 18 × 9 × x
x = 16 days

This Question Belongs to Arithmetic Ability >> Time And Work