If the optimistic time, most likely time and pessimistic time for activity A are 4, 6 and 8 respectively and for activity B are 5, 5.5 and 9 respectively, then

Answer & Solution
Correct Answer: Option C
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

1 Comment
Lisha Ghosh
Lisha Ghosh 5 years ago
Expected time of Activity A = (4+6*4+8)/6=36
Expected time of Activity B = (5+5.5*4+9) = 36
Hence, the Expected time of Activity A and B are same.