In crashing a CPM network, which of the following is true?
A. The first activity to be crashed is the highest expensive activity on the critical path
B. The last activity to be crashed is the least expensive activity on the critical path
C. When path with the lowest length can not be reduced further
D. None of the above
Answer: Option C