Key concept under which technique are network of events and activities , resource allocation, time and cost considerations, network paths and critical paths ?

A. Game Theory

B. Network Analysis

C. Decision Theory

D. None of the above

Answer: Option B

Solution (By Examveda Team)

Key concept under Network Analysis are network of events and activities , resource allocation, time and cost considerations, network paths and critical paths. Network analysis is any structured technique used to mathematically analyze a circuit (a “network” of interconnected components).

This Question Belongs to Management >> Operations Research