Match the following.
| List-I | List-II |
| a. Governance | 1. Developing a programme plan |
| b. Management | 2. Managing cost of programme |
| c. Financial Management | 3. Defining the programme roles |
| d. Infrastructure | 4. Planning the overall programme |
A. a-4, b-3, c-1, d-2
B. a-1, b-3, c-2, d-4
C. a-2, b-1, c-4, d-3
D. a-3, b-4, c-2, d-1
Answer: Option D