33.
A loose mineral deposit formed either by chemical weathering at the place of origin or formed by mechanical weathering of the ore body by the stream water. The deposit is known as

36.
Hydraulic ring main system is used to

37.
Maximum supports are required within 10 m of freshly-exposed roof-why?

40.
In an underground mine output from the panel is 360 tpd, having 26 days of working in a month where incubation period of coal is 9 month. If recovery from the panel is 80% and pillar size is 30 m × 30 m, height 3 m, coal sp. gravity 1.8 then find out number of pillars in the panel.