Naman does half the work as Gagan in 4/5 the time. If together they take 16 days to complete a piece of work, then how long will it take Gagan to complete the work?
A. 23 days
B. 24 days
C. 25 days
D. 26 days
Answer: Option D
A. 23 days
B. 24 days
C. 25 days
D. 26 days
Answer: Option D
A. 18 days
B. 24 days
C. 30 days
D. 40 days
Join The Discussion