ExamVeda
Login
Home
Construction Planning and Management
?

Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
Construction Planning and Management mcq question image

Answer & Solution
Correct Answer: Option B
Let's discuss the solution. Join the discussion
Examveda
Question posted by Examveda
Community

Join the Discussion

1 Comment
Riju Chakraborty
Riju Chakraborty 7 years ago
Latest occurrence time calculated from backward pass method.

Therefore TL of event 4 is 75 given;
Now( 75- (TE of 3-4) - (TE of2-3)),
TE =( opt time + 4 *most lik time + pess time) /6.
75 - (15) - (35) = 25 i.e TL of event 2 i.e asked