P can work thrice as fast as Q working independently, can complete a task in 24 days. In how many days can P and Q together finish the same task?
A. 5
B. 4
C. 6
D. 8
Answer: Option C
Solution (By Examveda Team)
\[\begin{array}{*{20}{c}} {}&{\text{P}}&{}&{\text{Q}} \\ {{\text{Efficiency}}}&3&:&1 \\ {{\text{Time}}}&1&:&3 \end{array}\]3 unit → 24 days
1 unit → 8 days
Total work = 24
P + Q can complete the same work = $$\frac{{24}}{4}$$ = 6 days