Pick up the correct statement from the following:
A. Forward pass is used for calculating earliest expected time
B. Backward pass is used for calculating the latest occurrence time
C. Maximum value of earliest expected time is used if there is more than one value of any event
D. All the above
Answer: Option D
The normal time required for the completion of project in the above problem is
A. 9 days
B. 13 days
C. 14 days
D. 19 days
A. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{2}$$
B. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{3}$$
C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{4}$$
D. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{5}$$
E. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$
A construction schedule is prepared after collecting
A. Number of operations
B. Output of labour
C. Output of machinery
D. All the above
A. 3.5 and $$\frac{5}{6}$$
B. 5 and $$\frac{{25}}{{36}}$$
C. 3.5 and $$\frac{{25}}{{36}}$$
D. 4 and $$\frac{5}{6}$$