Pick up the incorrect statement from the following:
A. An activity of a project is denoted by an arrow on the net work
B. The tail of the arrow indicates the start of the activity
C. The head of the arrow indicates the end of the activity
D. The arrows are drawn to scale from left to right
Answer: Option D
The normal time required for the completion of project in the above problem is
A. 9 days
B. 13 days
C. 14 days
D. 19 days
A. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{2}$$
B. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{3}$$
C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{4}$$
D. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{5}$$
E. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$
A construction schedule is prepared after collecting
A. Number of operations
B. Output of labour
C. Output of machinery
D. All the above
A. 3.5 and $$\frac{5}{6}$$
B. 5 and $$\frac{{25}}{{36}}$$
C. 3.5 and $$\frac{{25}}{{36}}$$
D. 4 and $$\frac{5}{6}$$