Select the correct statement.
A. Activity arrows in a CPM network are drawn to scale
B. The tail of an arrow represents the finish of an activity
C. Arrow bead represents the start of an activity
D. None of the above
Answer: Option D
The normal time required for the completion of project in the above problem is
A. 9 days
B. 13 days
C. 14 days
D. 19 days
A. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{2}$$
B. $$\frac{{{{\text{t}}_{\text{o}}} + 3{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{3}$$
C. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{4}$$
D. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{5}$$
E. $$\frac{{{{\text{t}}_{\text{o}}} + 4{{\text{t}}_{\text{m}}} + {{\text{t}}_{\text{p}}}}}{6}$$
A construction schedule is prepared after collecting
A. Number of operations
B. Output of labour
C. Output of machinery
D. All the above
A. 3.5 and $$\frac{5}{6}$$
B. 5 and $$\frac{{25}}{{36}}$$
C. 3.5 and $$\frac{{25}}{{36}}$$
D. 4 and $$\frac{5}{6}$$