The cross-section of a road partly in banking and partly in cutting is shown in the given figure. The area of the shaded portion is
A. $$\frac{1}{3} \times \frac{{{{\left( {{\text{b}} - {\text{rd}}} \right)}^2}}}{{{\text{r}} - {\text{s}}}}$$
B. $$\frac{1}{3} \times \frac{{{{\left( {{\text{b}} - {\text{rd}}} \right)}^2}}}{{{\text{r}} + {\text{s}}}}$$
C. $$\frac{1}{2} \times \frac{{{{\left( {{\text{b}} + {\text{rd}}} \right)}^2}}}{{{\text{r}} - {\text{s}}}}$$
D. $$\frac{1}{3} \times \frac{{{{\left( {{\text{b}} - {\text{rd}}} \right)}^2}}}{{{\text{s}} - {\text{r}}}}$$
Answer: Option A
A. Mid-section formula
B. Trapezoidal formula
C. Prismoidal formula
D. All the above
Size, capacity and materials need be specified for
A. Bib-cocks
B. Stop-cocks
C. Ball valves
D. All the above
The expected out turn of 12 mm plastering with cement mortar is
A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m
A. Excavation
B. Surface dressing
C. Cutting
D. Surface excavation
Join The Discussion