The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

A. 1.5 m3

B. 2.5 m3

C. 3.5 m3

D. 5.0 m3

Answer: Option D


This Question Belongs to Civil Engineering >> Estimating And Costing

Join The Discussion

Comments (1)

  1. Yaksharaj Naik
    Yaksharaj Naik:
    4 years ago

    Cc work 1:2:4- 5 m3