The following information is provided for an ore deposit:
Number of waste blocks = 10
Number of ore blocks = 5
Volume of each waste block, m3 = 600
Total cost of waste handling per m3 = Rs. 100
Tonnage of each ore block = 400
Total cost of ore handling per ton = Rs. 150
Sale price of ore per ton = Rs. 500
The net cash flow of mining the deposit in lakhs of rupees, is

A. 3.4

B. 2.5

C. 1.0

D. 0.8

Answer: Option C


This Question Belongs to Mining Engineering >> Mine Economics