The most creative and challenging phase of system life cycle is ___________.
A. Feasibility study
B. Maintenance
C. Design
D. None of the above
Answer: Option C
A. Feasibility study
B. Maintenance
C. Design
D. None of the above
Answer: Option C
A. Management level system
B. Operational level system
C. Knowledge level system
D. Strategic level system
A. Decision Support System (DSS)
B. Management Information System (MIS)
C. Executive Support System (ESS)
D. Transaction Processing System (TPS)
A. Decision Support System (DSS)
B. Management Information System (MIS)
C. Executive Support System (ESS)
D. Transaction Processing System (TPS)
A. Knowledge workers
B. Executives
C. System analysts
D. Data workers
Join The Discussion