The most creative and challenging phase of system life cycle is ___________.
A. Feasibility study
B. Maintenance
C. Design
D. None of the above
Answer: Option C
Solution(By Examveda Team)
The most creative and challenging phase of system life cycle is Design. It refers to the technical specifications that will be applied in implementing the candidate system. It also includes the construction of programmers and program testing.Related Questions on Management Information System (MIS)