Examveda

To do a certain work, A and B work on alternate days, with B beginning the work on the first day. A can finish the work alone in 48 days. If the work gets completed in $$11\frac{1}{3}$$ days, then B alone can finish 4 times the same work in:

A. 24 days

B. 32 days

C. 27 days

D. 30 days

Answer: Option C

Solution (By Examveda Team)

Let total work = 48 unit
Time and Work mcq question image
B × 6 + A × $$\frac{{16}}{3}$$ = 48
B × 6 + 1 × $$\frac{{16}}{3}$$ = 48
B × 6 = $$\frac{{128}}{3}$$
B = $$\frac{{64}}{9}$$
4 × Total work = B × Days
Now, 48 × 4 = $$\frac{{64}}{9}$$ × Days
27 = Days

This Question Belongs to Arithmetic Ability >> Time And Work

Join The Discussion

Related Questions on Time and Work