Total Quality Management (TQM) programmes are more likely to remain effective if a number of prescriptions are followed. Which of the following prescriptions should not be followed?
A. TQM does not become a separate 'bolt-on' set of activities
B. Slogans and exhortations about TQM's effectiveness are avoided
C. TQM should become a substitute for normal managerial leadership
D. Quality improvement relates to an operation's performance objectives
Answer: Option C