Two persons having different productivity of labour, working together can reap a field in 2 days. If one-third of the field was reaped by the first man and rest by the other one working alternatively took 4 days. How long did it take for the faster person to reap the whole field working alone?

Answer & Solution
Correct Answer: Option A
Total efficiency of two persons = 50% [As they complete work in 2 days. ]
First Person completes work = $$\frac{1}{3}$$ = 33.33% [In 2 days]
Rest work will be completed by Second man = $$\frac{2}{3}$$ = 66.66% [In 2 days]
So, efficiency of second person is greater.
Efficiency of second person = $$\frac{{66.66}}{2}$$  = 33.33% per day
Then, Second person will complete whole work in,
= $$\frac{{100}}{{33.33}}$$  = 3 days.
Examveda
Question posted by Examveda
Community

Join the Discussion

2 Comments
Md Mahabubor
Md Mahabubor 7 years ago
A=1/3
B=2/3
23 part is completed 4days
Then whole by 2nd man = 3/2*4=6
First man's part= 1/2-1/6=1/3
Answer : 3day
Md Ibrahim
Md Ibrahim 8 years ago
1/3---4=12 days
1-1/3=2/3---4=6 days
1/6----1 day
1/2----6/2=3 days.