Examveda
Examveda

Two worker A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take $${\text{4}}\frac{1}{2}$$ hours more than when working together. The time required to finish the work together is = ?

A. 5 hours

B. 8 houras

C. 4 hours

D. 6 hours

Answer: Option D

Solution(By Examveda Team)

$$\eqalign{ & {\text{Let,}} \cr & {\text{a}} = {\text{8h}} \cr & {\text{b}} = {\text{4}}\frac{1}{2}{\text{h}} = \frac{9}{2}{\text{h}} \cr} $$
Time required to finish the work together
$$\eqalign{ & = \sqrt {{\text{ab}}} \cr & = \sqrt {8 \times \frac{9}{2}} \cr & = 6{\text{ h}} \cr} $$

This Question Belongs to Arithmetic Ability >> Time And Work

Join The Discussion

Related Questions on Time and Work